Project status
Stage 1 has commenced and is due for completion in August 2026.
Stay up to date
Provide your feedback
We are seeking feedback on the requirements when removing and replacing welded panels.
Survey closes Wednesday 16 July 2025
Key stages of the work
Stage 1 includes:
-
developing a consultation strategy
-
establishing a Technical Advisory Group (TAG)
-
consulting with stakeholders
-
preparing draft training product.
Start: May 2025
End: August 2025
Stage 2 includes:
-
releasing draft training products for public and government consultation
-
reviewing feedback with the TAG.
Start: September 2025
End: September 2025
Stage 3 includes:
-
implementing feedback and finalising the training product
-
consulting with Commonwealth or state and territory Senior Responsible Officers.
Start: October 2025
End: February 2026
Stage 4 includes:
-
submitting training products to the Assurance Body
-
uploading the endorsed training products to the National Training Register following endorsement of the training products by Skills Ministers.
Start: March 2026
End: May 2026
Stage 5 includes:
- Promotion, implementation and monitoring of the endorsed training products
Start: Monday 1 June 2026
End: Monday 31 August 2026