Stage 1 has commenced and is due for completion in March 2026.
Key stages of the work
Stage 1 includes:
Developing a consultation strategy, establishing a Technical Committee, targeted consultation with stakeholders, and reviewing and providing feedback on Technical Committee.
Drafting revised Training Products addressing mine site supervision competencies.
Start: October 2025
End: March 2026
Stage 2 includes:
Draft Training Products released for public and government consultation for a minimum 4-week period.
Start: April 2026
End: April 2026
Stage 3 includes:
- Implement feedback with Technical Committee.
- Undertake additional consultation and draft final version of Training Products.
- Consultation with commonwealth or state and territory Senior Responsible Officers (SROs).
- Final compliance check of the products and preparation of the Training Products for submission to the Assurance Body.
Start: May 2026
End: October 2026
Stage 4 includes:
- Submit Training Products for endorsement by the Assurance Body
- Upload the endorsed Training Products to the National Training Register
Start: November 2026
End: January 2027
Stage 5 includes:
Promoting, implementing and monitoring the endorsed Training Products
Start: February 2027
End: March 2027