Project status
Stage 2 has commenced and is due for completion in April 2025.
Key stages of the work
Stage 1 includes:
- Project planning
- Developing the consultation strategy
- Performing initial data analysis
Start: February 2024
End: June 2024
Stage 2 includes:
- Updating data with 2023 enrolment data and renewing data analysis
- Public and government consultation
- Produce and submit the draft report and options paper to DEWR
Start: November 2024
End: April 2025
Stage 3 includes:
- Seeking support from Senior Responsible Officers/State Training Authorities
- Submit training products for endorsement by Assurance Body
- Actioning any deletions on the National Training Register of training products with low or no enrolments
Start: May 2025
End: June 2025